CDBG-DR Process Implementation Timeline

4/12/16

1st Town Hall/Public Meeting

4/16/16

2nd Town Hall/Public Meeting

6/17/16

Federal Register publication

6/22/16          

Effective Date of Federal Register (day 1 of 90 day process)

6/20 – 6/21/16

Technical Assistance Meetings – HUD/Capital Access

6/22/16

1st Needs Assessment Task Force Meeting

7/6/16

3rd Town Hall/Public Meeting

7/7/16

2nd Needs Assessment Task Force Meeting

7/25/16          

Council Workshop to hear NA Results/Funding Implications                                                                      

8/2/16

Council Action to Award Action Plan allocations

8/3 – 8/18/16

Time to complete Action Plan Draft

8/19 – 9/2/16

Action Plan posted to City website; 14 Day Comment Period

9/6/16

City Council briefing on Action Plan Comments and Responses

9/6 – 9/7/16

Finalize Action Plan, reproduce copies, obtain City Manager’s signature

9/8/16

Federal Express Action Plan to HUD

9/9/16

HUD Receives Action Plan

9/20/16

True deadline to have Action Plan delivered to HUD[MM1] 

10/24/16

HUD Approval of Action Plan (45 days from date of submission)

November 2016

Begin Implementation and Program Design (following Action Plan approval)

No earlier than the 1st Quarter of 2017

Begin Program Roll-Out

2022

Program Closeout

                                                                                  7/27/2016