Project Update

Project Name: Victory Gardens Subdivision Improvements

Current Update: 08/2021

Work Completed Last Month: Complete electric work/services along Patton Street from Roosevelt to Railroad. 

Work Planned This Month: Working on preliminary punch list items including water meter adjustments, brick mailbox installation, storm drain clean up, stops signs installation and pavement repairs

Construction Completion: See Dashboard For Details

Pictures from last month:


072721 Patton Roosevelt Concrete Valley Gutter Pre Pour (2)072621 Macarthur Working list Walk Thru (1)072221 Concrete Pre Pour 500 Block Patton (2)