Project Update 

Project Name: Guadalupe Street Improvements - Bike Lane Signals

Current Update: 12/2021

Work Completed Last Month: Conduits and pull box installation, bike lane signal installations 

Work Planned This Month: Complete signal phasing and timing

Construction Completion: See Dashboard for Details

Island ready for concrete at MLK and LBJCorner of Guadalupe and San Antonio after being cleaned up. Light base is under the barrel for safetConduit being installed along Guadalupe st and MLK