Project Name: Rio Vista Falls Maintenance

Current Update: 12/2021

Work Completed Last Month: Crews set up the bypass pipe outfall along trhe riverbed protection near the Cheatham Street bridge. 

Work Planned This Month: Crews will open the bypass system and begin the dewatering process. Restoration work will begin on the uppermost spillway/pool. 

Construction Completion: See Dashboard for Details

Pictures from last month:

Cofferdam setup for testing gatesSweeping for Fountain DartersCofferdam setup for testing gates (2)